Body and Paint

Rear Roof Frame. Removal and Installation

10steps
~60min
3/5difficulty
Done 0 of 10

Special Service Tools / General Equipment

Resistance Spot Welding Equipment
Spot Weld Drill Bit
Locking Pliers

Removal

NOTICE: Battery electric vehicles (BEV), hybrid electric vehicles (HEV) and plug-in hybrid electric vehicles (PHEV) contain a high-voltage battery. Before cutting or welding near the high-voltage battery, it must be removed to prevent damage.

  1. Disable the SRS.
    Refer to: Disabling and Enabling the Supplemental Restraint System (SRS) (501-20B Supplemental Restraint System, General Procedures).
  2. If necessary:
    Restore the vehicle dimensions to their pre-damage condition.
    Refer to: Body and Frame (501-26 Body Repairs - Vehicle-Specific Information and Tolerance Checks, Description and Operation).
  3. Remove the roof.
    Refer to: Roof Panel (501-28 Roof Sheet Metal Repairs, Removal and Installation).
    Refer to: Roof Panel - Vehicles With: Roof Opening Panel (501-28 Roof Sheet Metal Repairs, Removal and Installation).
  4. Remove the welds.
    Use common equipment: spot weld drill bit
    Ford Fusion. Roof Rear Frame. Removal and Installation
  5. Remove the rear roof frame.
    Ford Fusion. Roof Rear Frame. Removal and Installation

Installation

NOTICE: Battery electric vehicles (BEV), hybrid electric vehicles (HEV) and plug-in hybrid electric vehicles (PHEV) contain a high-voltage battery. Before cutting or welding near the high-voltage battery, it must be removed to prevent damage.

NOTICE: The high-voltage battery in a battery electric vehicle (BEV), hybrid electric vehicle (HEV) or plug-in hybrid electric vehicle (PHEV) can be affected and damaged by excessively high temperatures. Temperatures in the paint booths of some body shops may exceed 60 °C. Therefore, during paint work the paint booth temperature must be set to 60 °C or lower, with a bake time of 45 minutes or less. A temperature above 60 °C or a bake longer than 45 minutes requires removing the high-voltage battery from the vehicle before placing it in the paint booth.

NOTICE: If the paint curing temperature exceeds 60 °C, the charge port indicator ring on plug-in vehicles must be removed.

  1. Install, position and secure the rear roof bow.
    Use common equipment: locking pliers
    Ford Fusion. Roof Rear Frame. Removal and Installation
  2. Install the welds.
    Use primary equipment: resistance spot welding equipment.
    Ford Fusion. Roof Rear Frame. Removal and Installation
  3. Seam Sealing: All seams must be sealed to production level.
  4. Install the roof.
    Refer to: Roof Panel (501-28 Roof Sheet Metal Repair, Removal and Installation).
    Refer to: Roof Panel — Vehicles with: Roof Opening Panel (501-28 Roof Sheet Metal Repair, Removal and Installation).
  5. Reset the SRS.
    Refer to: Disabling and Enabling the Supplemental Restraint System (SRS) (501-20B Supplemental Restraint System, General Procedures).

Test yourself

A quick Ford Fusion quiz: every answer comes with an explanation and a link to the manual page.