Ignition

Ignition coil

~1min read
010203040507.56N·mlb·ft
Tightening torque found on this page

COMPONENTS

COMPONENTS

INSTALLATION

Installation is in the reverse order of removal. ( IG-6 )

REMOVAL

1. REMOVE V-BANK COVER

2. REMOVE INTAKE AIR CONNECTOR

3. DISCONNECT ENGINE WIRE FROM LH CYLINDER HEAD COVER

Disconnect the 2 wire clamps and engine wire.

4. DISCONNECT IGNITION COIL (WITH IGNITER) CONNECTORS

DISCONNECT IGNITION COIL (WITH IGNITER) CONNECTORS

5. REMOVE IGNITION COILS (WITH IGNITER) FROM SPARK PLUGS

Remove the bolt, and pull out the ignition coil (with igniter). Remove the 8 ignition coils (with igniter).

Torque: 7,5 N·m

Test yourself

A quick Toyota Land Cruiser quiz: every answer comes with an explanation and a link to the manual page.