Electrical & Power Control

Charging System Preliminary Inspection

~1min read
Diagnosis Procedure

CHECK BATTERY TERMINAL CONNECTIONS

Check if battery terminals are clean and tight.

Is the inspection result normal?

YES>>

GO TO 2.

NO>>

Repair battery terminals connection. Confirm repair by performing system test using 165-DSS-5000P. Refer to the applicable instruction manual for proper testing procedures.

CHECK FUSE AND FUSIBLE LINK

Check for blown fuse and fusible link.

UnitPower source (Power supply terminals)Fuse or Fusible Link No.Capacity
Generator Battery (terminal 3) 59 10 A
Battery (terminal 1) A 250 A
Combination meter Ignition switch ON or START (terminal 2) 31 5 A

Is the fuse or fusible link blown?

YES>>

Replace the blown fuse or fusible link after repairing the affected circuit.

NO>>

GO TO 3.

CHECK GENERATOR GROUND

Check if generator case ground is clean.

Is the inspection result normal?

YES>>

GO TO 4.

NO>>

Repair connection.

CHECK DRIVE BELT TENSION

Check drive belt tension. Refer to Inspection.

Is the inspection result normal?

YES>>

Inspection End.

NO>>

Repair as needed.