Engine

Pair reed valve removal and installation

3steps
~18min
2/5difficulty
01020304050107N·mlb·ft
Tightening torque found on this page
Done 0 of 3
Removal
  1. Lift and support the fuel tank with the prop stay.

    Refer to “fuel tank removal and installation” in section 1g .

  2. Remove the air cleaner box. Refer to “air cleaner box removal and installation” in section 1d .
  3. Remove the pair control solenoid valve (1) along with the pair reed valve covers (2). Refer to “pair control solenoid valve removal and installation” .
    Suzuki GSX-R. Pair reed valve removal and installation

  1. Remove the pair reed valves (3).
Suzuki GSX-R. Pair reed valve removal and installation

Installation

Install the pair reed valve in the reverse order of removal. Pay attention to the following points:

  • apply thread lock to the pair reed valve cover bolts and tighten them to the specified torque.
: Thread lock cement
99000–32110 (thread lock cement super “1322” or equivalent)
Tightening torque pair reed valve cover bolt (a): 10 N·m
Suzuki GSX-R. Installation