K114 Continuously Variable Transmission

Removal

~4min read

REMOVAL

PRECAUTION / NOTICE / HINT

The procedures required (adjustment, calibration, initialization or registration) that must be performed after parts are removed, installed or replaced during gear shift control cable assembly removal/installation are shown below.

Procedure Required After Replacing / Removing / Installing Parts

Replacement part or procedure

Required Procedure

Effect/Inoperative function when procedure not performed

Link

Disconnect the cable from the negative (-) battery terminal.

Initialize Back Door Lock

Door Lock Control System

Memorize Steering Angle Neutral Point

Lane Departure Alert System (with Steering Control)

Pre-Collision System

Gas leak in the exhaust system

Verification after Repair

  • Poor idling, etc.
  • Engine start function, etc.

CAUTION:

  • When the engine is hot, do not touch high-temperature areas such as the engine or exhaust pipe.
  • Contact with high-temperature areas such as the engine and exhaust pipe may cause burns.

PROCEDURE

1. PRECAUTIONS

NOTICE:

After turning the ignition switch OFF, a waiting time may be required before disconnecting the cable from the negative (-) battery terminal. Therefore, be sure to read the precautions for disconnecting the cable from the negative (-) battery terminal before performing the work.

Click here

2. SECURE VEHICLE

(a) Fully apply the parking brake and chock a wheel.

CAUTION:

  • Be sure to apply the parking brake and chock a wheel before performing this operation.
  • If the vehicle is not secured and the shift lever is moved to the N position, the vehicle may move suddenly and cause an accident or serious injury.

3. DISCONNECT BATTERY NEGATIVE TERMINAL CABLE

Click here

NOTICE:

When the cable has been disconnected, some systems must be reset after the cable is reconnected.

Click here

4. REMOVE BATTERY

Click here

5. REMOVE SHIFT LEVER KNOB SUB-ASSEMBLY

Click here

6. REMOVE REAR CONSOLE BOX ASSEMBLY

Click here

7. REMOVE ENGINE UNDER COVER NO. 1

Click here

8. REMOVE ENGINE UNDER COVER REAR LH

Click here

9. REMOVE VALVE COVER NO. 2

Click here

10. REMOVE RADIATOR COVER

Click here

11. REMOVE AIR CLEANER INLET NO. 1

Click here

12. REMOVE AIR CLEANER COVER WITH AIR CLEANER HOSE

Click here

13. REMOVE AIR CLEANER CASE SUB-ASSEMBLY

Click here

14. REMOVE ECM

Click here

15. REMOVE BATTERY CLAMP SUB-ASSEMBLY

Click here

16. REMOVE FRONT FLOOR LH COVER (with cover)

Click here

17. REMOVE FRONT FLOOR RH COVER (with cover)

HINT:

Perform the same procedure as for the left side.

18. REMOVE FRONT FLOOR CENTER BRACE

Click here

19. REMOVE FRONT EXHAUST PIPE ASSEMBLY (TWC: front and rear catalytic converter)

Click here

20. REMOVE FRONT FLOOR HEAT INSULATOR NO. 1

(a) Remove the 3 nuts and the front floor heat insulator No. 1 from the vehicle body.

21. REMOVE GEAR SHIFT CONTROL CABLE ASSEMBLY

(a) Place the shift lever in the N position.

Remove in this direction

(b) Disconnect the end of the gear shift control cable assembly from the floor shift lever assembly.

*1

Slider

Push in

Remove in this direction

(c) Push the slider and remove the gear shift control cable from the floor shift lever assembly as shown in the illustration.

(d) Remove the nut to disconnect the gear shift control cable assembly from the control shaft lever.

(e) Remove the clip to disconnect the gear shift control cable assembly from the gear shift control cable bracket No. 1.

(f) Remove the nut to disconnect the gear shift control cable assembly from the gear shift control cable bracket.

(g) Remove the nut.

(h) Release the guide to disconnect the gear shift control cable assembly from the vehicle body.

(i) Remove the 2 nuts and the gear shift control cable assembly from the vehicle body.