Meters / Gauges / Display

Installation

~1min read

INSTALLATION

PROCEDURE

1. INSTALL COMBINATION METER ASSEMBLY

(a) Connect the 2 connectors to install the combination meter assembly.

(b) Engage the guides and clips.

(c) Install the 2 screws.

2. INSTALL INSTRUMENT PANEL FINISH SUB-ASSEMBLY NO. 2

Click here

3. INSTALL COMBINATION METER FINISH PANEL ASSEMBLY

Click here

4. INSTALL INSTRUMENT CLUSTER FINISH PANEL GARNISH ASSEMBLY

Click here

5. INSTALL COMBINATION METER FINISH PANEL SUB-ASSEMBLY

Click here

6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

Click here

NOTICE:

When the cable has been disconnected, some systems must be reset after the cable is reconnected.

Click here