Installation
INSTALLATION
PROCEDURE
1. INSTALL OIL CLEANER MAGNET (CVT)
(a) Install the 2 oil cleaner magnets (CVT) to the CVT transaxle oil pan sub-assembly. |
|
2. INSTALL CVT TRANSAXLE OIL PAN SUB-ASSEMBLY
(a) Clean the mating surface of the CVT transaxle oil pan sub-assembly and the CVT transaxle assembly.
(b) Install a new CVT transaxle oil pan gasket onto the CVT transaxle oil pan sub-assembly.
(c) Install the CVT transaxle oil pan sub-assembly onto the CVT transaxle assembly using the 19 bolts.
Torque:
7.5 N·m {76 kgf·cm, 66 in·lbf}
(d) Using a 6 mm hexagon socket wrench, install the No. 1 transmission oil filler pipe onto the CVT transaxle oil pan sub-assembly.
Torque:
1.7 N·m {17 kgf·cm, 15 in·lbf}
(e) Using a 6 mm hexagon socket wrench, temporarily install the gasket and overflow plug onto the CVT transaxle oil pan sub-assembly.
HINT:
Reuse the old gasket, as the overflow plug will need to be removed again to adjust the fluid level.
(f) Using a 10 mm hexagon socket wrench, install a new gasket and the drain plug onto the CVT transaxle oil pan sub-assembly.
Torque:
49 N·m {500 kgf·cm, 36 ft·lbf}
3. ADD CVT FLUID
Click here![]()
4. CHECK FOR FLUID LEAKS
5. INSTALL ENGINE UNDER COVER REAR LH
Click here
![]()
6. INSTALL ENGINE UNDER COVER SUB-ASSEMBLY NO. 1
Click here
![]()