Air conditioning

Connecting flange

~2min read

B84 ou C84 ou S84

Essential equipment

charging station

Tightening torques

connecting flange mounting bolt 0.8 daN.m
pipe connection fixing bolts 0.8 daN.m
battery cover bolts 0.4 daN.m

REMOVAL

  • Disconnect the battery, starting with the negative terminal.
  • Remove the engine covers.
  • Drain the refrigerant circuit using a recovery/recharge station.

F9Q or K4M or K9K

Bride de liaison
  • Unclip the sound insulation from the bulkhead.
  • Unscrew the pipe connections (1) from the connecting flange.
  • Disconnect the pipes.
  • Fit plugs to the openings.

K4J

Bride de liaison
  • Remove the air box (2) (Chapter Fuel Mixture).
  • Release the fuel cut-off solenoid valve (3).
Bride de liaison
  • Unclip the sound insulation from the bulkhead.
  • Unscrew the pipe connections (4) from the connecting flange.
  • Disconnect the pipes.
  • Fit plugs to the openings.

F4R

Bride de liaison
  • Remove:
  • the wiper arms,
  • the left and right pillars.
Bride de liaison
  • Remove:
  • the bulkhead seal (5),
  • the plastic rivets (6),
  • the cowl grille (7).
Bride de liaison
  • Remove:
  • the mounting clips (8) of the water box cover,
  • the water box cover (9),
  • the heat shield mountings.
Bride de liaison
  • Unscrew the pipe connections (10) from the connecting flange.
  • Disconnect the pipes.
  • Fit plugs to the openings.
Bride de liaison
  • Remove the two connecting flange mounting bolts (11).
  • Refit a pipe connection bolt in order to extract the connecting flange.
  • Remove the O-rings from the evaporator pipes.

INSTALLATION

Bride de liaison
  • Refit the O-rings onto the pipes (12).
  • Refit in the reverse order of removal.
  • Gradually tighten the two connecting flange mounting bolts so that the connecting flange is evenly pressed onto the pipes.
  • Check that the seal seating surfaces on the connecting flange and the sealing gaskets are in good condition.
  • Replace the seals.
  • Lubricate with the recommended air conditioning oil to ease fitting.

Note: Any damaged seal requires replacement of the pipe.

  • Tighten to the following torques:
  • the connecting flange mounting bolt (0.8 daN.m),
  • the pipe connection mounting bolts (0.8 daN.m),
  • the battery cover bolts (0.4 daN.m).
WARNING

Connect the battery; carry out the necessary relearn procedures (Chapter Battery).

  • Refill the refrigerant circuit using a recovery/recharge station.
Note:
  • Check the air conditioning operates correctly with the fan unit at maximum speed.
  • If there is no cooling, carry out a leak check (see Air Conditioning chapter).
Note: When replacing a connecting flange, add 10 ml of the recommended oil to the quantity recovered.

Test yourself

A quick Renault Megane quiz: every answer comes with an explanation and a link to the manual page.