Battery Control System (Standard)

High Voltage Battery System

84steps
~504min
4/5difficulty
050100150200250154.9114N·mlb·ft
Tightening torque found on this page
Done 0 of 84

Contents:

Specification. Components and Components Location

Specification

Specification

Item Specification
Rated capacity (Ah) 120.6
Rated voltage (V) 523
Rated energy (kWh) 63
Cell capacity (Ah) 60.3
Composition 144 cells (24 modules)

Components and Components Location

Component

1. Main Fuse
2. Sub-Battery Pack Assembly (Sub-BPA)
3. Battery Module Assembly (BMA)
4. Battery Management Unit (BMU)
5. Power Relay Assembly (PRA)
6. Cell Monitoring Unit (CMU)

Description and Operation. Circuit Diagram

Description and Operation

Description

System Component
  • The high voltage battery system supplies power to the drive motor when the EV is driving or stopped and to electric devices used in the vehicle.
  • The battery is composed of the cell, which is the smallest unit, and the module which is combined with cells. The high voltage system consists of the battery pack that is made up of modules, and it is also called the Battery System Assembly (BSA).
  • It consists of 6 Sub Battery Pak Assembly (Sub-BPA), the Battery Management Unit (BMU) for managing the 24 battery modules, the Cell Monitoring Unit (CMU), and the Power Relay Assembly (PRA).
Battery System Assembly Component
  • Sub Battery Pack Assembly (Sub-BPA) - 6 packs - Pack Number
  • Battery Module Assembly (BMA) - 24 modules (2P6S) - Module Number
  • Cell - 144 cells - Cell Number

Circuit Diagram

Circuit Diagram

Battery Module Assembly (BMA) Components and Components Location

Component

1. Upper Case Bolt
1-a. 103.0 - 155 N·m
2. O-Ring
3. Upper Case
3-a. Step 1 : 8,8 N·m
3-a. Step 2 : 10,8 N·m
4. Waterproof Gasket
5. Sub Battery Pack Assembly (Sub-BPA)
5-a. Step 1 : 8,8 N·m
5-a. Step 2 : 10,8 N·m
6. Battery Module Assembly (BMA)
6-a. 7.8 - 11,8 N·m

Battery Module Assembly (BMA) Removal and Installation

Special Service Tool

Tool Name / Number Illustration Description
High voltage Battery Module Assembly (BMA) transport hanger
TKS - 2301
Used to transferring the high voltage Sub Battery Pack Assembly (Sub-BPA) and Battery Module Assembly (BMA)
High voltage battery module surface pressure jig
09375 - GI800
Used for compressing the high voltage Sub Battery Pack Assembly (Sub-BPA)
High voltage battery module guide
09375 - GI900
Used for seating the high voltage battery module on the surface pressure jig
High voltage battery module disassembly jig
TMS - 1907
Used for disassembling the high voltage Sub Battery Pack Assembly (Sub-BPA)

Removal

  • When working on the high voltage system, the work should be performed by technicians who have completed the relevant training. A lack of understanding of the high voltage system can lead to serious accidents due to electric shock or short circuit.
  • When working on the high voltage system or related components, be sure to observe and be aware of the "Safety Precautions, Cautions and Warnings". If not, it may cause serious accidents due to electric shock or short circuit.
  • When working on high voltage system, make sure to check the Personal Protective Equipment (PPE) and high voltage shut-off procedure.
Install the high voltage battery module surface pressure jig and guide before using the high voltage battery module disassembly jig. (Refer to the equipment manufacturer's manual)
  1. Remove the Sub-Battery Pack Assembly (Sub-BPA). (Refer to High Voltage Battery System - "Sub Battery Pack Assembly (Sub-BPA)")
  2. Remove the Battery Module Assembly (BMA) transport hanger(TKS - 2301) (A).
  3. Rotate the jig handle to clockwise to apply Sub-BPA (A) surface pressure.
    Specified torque : 4.9 - 6,9 N·m (0.5 - 0.7 kgf·m, 3.6 - 5.1 lb·ft, 43.4 - 60.8 lb·in)
  4. Remove the BMA (A) after removing the bolts.

    Tightening torque : 7.8 - 11,8 N·m

  5. Visually inspect the underside of the BMA, and if there is any deformation, replace the BMA with a new one.
    When using the deformed battery modules may result in fire, so replace them with new ones.

Installation

  • When working on the high voltage system, the work should be performed by technicians who have completed the relevant training. A lack of understanding of the high voltage system can lead to serious accidents due to electric shock or short circuit.
  • When working on the high voltage system or related components, be sure to observe and be aware of the "Safety Precautions, Cautions and Warnings". If not, it may cause serious accidents due to electric shock or short circuit.
  • When working on high voltage system, make sure to check the Personal Protective Equipment (PPE) and high voltage shut-off procedure.
  1. Perform the cell balancing procedures when the Battery Module Assembly (BMA) is replaced with a new one. (Refer to Battery Module Assembly (BMA) - "Adjustment")
  2. Apply a new gap filler with the Special Service Tool (SST). (Refer to High Voltage Battery System - "Gap Filler Application")
  3. Install in the reverse order of removal.
    • Install the Battery Module Assembly (BMA) to the specified torque.
    • If the BMA is dropped, it may cause internal damage. (Do not reuse)
    • When installing the BMA, tighten the bolts in the following order while pressurized.
  4. Perform the High Voltage Battery Pack Connector Check with the KDS before installing the Battery System Assembly (BSA) upper case. (S/W Management → Battery Management System (BMS) → High Voltage Battery Pack Connector Check)
  5. Perform the air tightness inspection with the KDS. (Refer to High Voltage Battery System - "Air Tightness Inspection")
  6. Perform the SOC calibration with the KDS. (S/W management → Battery Management System (BMS) → SOC Calibration)
    Refer to the KDS screen for operating conditions and details.

Battery Module Assembly (BMA) Adjustment

Special Service Tool

Tool Name Illustration Description
High voltage battery module balancer
Tool & Tech T2000
Charging/discharging a new module when replacing a high-voltage battery module
(Balancing a new module to reduce the voltage difference with existing battery module)

Adjustment

Battery Cell Balancing Procedures

  1. Measure the voltage of 4 good Battery Module Assembly (BMA) by using the digital tester.
  2. Calculate the target voltage by using the measured value.

    Target Voltage (V) : A ÷ 4 A : Sum of voltages of the 4 good BMA

    • Do not need to calculate the maximum and minimum voltage with the KDS because the target voltage is calculated after measuring the voltage of normal battery module.
    • Do not need to calculate the individual cell voltage because the number of all BMA is the same.
  3. Perform the battery module balancing after installing the BMA to the xEV Battery Module Balancer then putting the target voltage in it.
    Charge/discharge the battery module after securing enough space around the xEV Battery Module Balancer.
  4. Compare the new battery module voltage and the target voltage with the digital tester, after completing the BMA balancing.

Battery System Assembly (BSA) Components and Components Location

Component Location

1. Battery Outlet Cooling Hose
2. Battery Inlet Cooling Hose
3. Front High Voltage Junction Box Power Cable
4. Battery Management Unit (BMU) Connector
5. Rear High Voltage Junction Box Power Cable
6. Integrated Charging Control Unit (ICCU) Power Cable
7. Battery System Assembly (BSA) Ground Cable
7-a. 7.8 - 11,8 N·m
8. Battery System Assembly (BSA)
8-a. 68.6 - 88 N·m
8-b. 117.7 - 137 N·m

Battery System Assembly (BSA) Description and Operation

Description

  • Battery System Assembly (BSA) is the battery that supplies the electric for driving the EV.
  • This is a device that charges and discharges the electricity supplied to the EV.
  • Battery modules have standard and long range types.
  • The system, which is combined with several battery modules, is called Battery Pack Assembly (BPA).
High Voltage Battery System Internal
  • There are a total of 6 battery packs connected.
  • The number of cells depends on the standard type and the long-range type. (Standard : 144 cells, Long range : 192 cells)
  • The battery module is connected to 2P6S (2 parallel 6 series).
  • The number of modules is 24 for standard and 32 for long range.
  • The main fuse cuts the high voltage circuit by separating the battery module to the left and right.
  • The interior is connected by bus bars. The Power Relay Assembly (PRA) and quick charging relay are connected to supply power.
    • Under the battery pack, a separate space is installed with a cooling cooler to circulate the coolant, ensuring safety regarding cooling and leakage.
    • Rated energy (kWh) = Rated capacity (120.6 Ah) * Rated voltage (523 V) = 63,073.8 / 1,000 = 63.0 (kWh)

Battery System Assembly (BSA) Removal and Installation

Special Service Tool

Tool Name / Number Illustration Description
High voltage Battery System Assembly (BSA) transport hanger
09375 - K4100
Used for transporting the high voltage Battery System Assembly (BSA)
High voltage Battery System Assembly (BSA) guide pin
09375 - BF000
Used for seating the high voltage Battery System Assembly (BSA) on the vehicle

Removal

  • When working on the high voltage system, the work should be performed by technicians who have completed the relevant training. A lack of understanding of the high voltage system can lead to serious accidents due to electric shock or short circuit.
  • When working on the high voltage system or related components, be sure to observe and be aware of the "Safety Precautions, Cautions and Warnings". If not, it may cause serious accidents due to electric shock or short circuit.
  • When working on high voltage system, make sure to check the Personal Protective Equipment (PPE) and high voltage shut-off procedure.
  1. Perform the high voltage shut off procedure. (Refer to Battery Control System - “High Voltage Shut-off Procedure”)
  2. Drain the high voltage battery coolant. (Refer to Cooling System - "High Voltage Battery Coolant")
  3. Separate the high voltage battery system coolant hoses (A).
    • Block the the high voltage battery connector by using isolation cover to prevent entering the coolant.
    • Collect coolant using a clean beaker (be careful not to mix other mixtures with coolant).
    • When the coolant enters the high voltage connector, make sure to clean it and then connect the connector.
  4. Disconnect the Integrated Charge Control Unit (ICCU) connector (A).
    How to disconnect the connector
    1. Release the locking clip (A) by pulling it.
    2. Disconnect the connector while pressing the locking clip (B).
  5. Disconnect the rear high voltage junction box power cable (A).
    How to disconnect the connector
    1. Release the locking clip (A) by pulling it.
    2. Disconnect the connector by pushing the lever (A) in the direction of the arrow while pressing the locking clip (B).
  6. Disconnect the Battery Management Unit (BMU) connector (A).
  7. Separate the Battery System Assembly (BSA) ground cable (A) by removing the bolt.

    Tightening torque : 7.8 - 11,8 N·m

    This procedure is applicable only to BSA with an installed grounding cable.
  8. Remove the BSA penetrate bolts (A).

    Tightening torque : 68.6 - 88 N·m

    Remove only the central bolts of the BSA for lift installation.
  9. Support the BSA using the lift (A).
    • Place an insulating mat (or rubber mat) on the lift and remove the battery. If there is foreign substance in the lower protection case, the protection case may be broken due to the battery load, but damage to the battery can be prevented with the insulating mat (or rubber mat).
    • Use a lift with a permissible payload of 700 kg (1543.23 lb) or above and a width of 0.7 m (27.56 in.) to 1.15 m (45.27 in.).
  10. Remove the BSA (A) by lowering the jack slowly after removing the bolts.

    Tightening torque : 117.7 - 137 N·m

    When removing the BSA, be careful not to damage other parts.
  11. Lift the BSA after installing SST (09375 - K4100), then using the crane jack.
    • Do not lift the BSA too much.
    • Be careful not to rotate the BSA while it is lifted.
    • When moving the BSA, move it on the lift and then lift it using a crane jack.
    • Put the BSA on the flat insulated mat or pallets to prevent the damage. (Do not transfer the crane jack)

Installation

  • When working on the high voltage system, the work should be performed by technicians who have completed the relevant training. A lack of understanding of the high voltage system can lead to serious accidents due to electric shock or short circuit.
  • When working on the high voltage system or related components, be sure to observe and be aware of the "Safety Precautions, Cautions and Warnings". If not, it may cause serious accidents due to electric shock or short circuit.
  • When working on high voltage system, make sure to check the Personal Protective Equipment (PPE) and high voltage shut-off procedure.
  1. Put the Battery System Assembly (BSA) on the lift by using the SST (09375 - K4100) and crane jack.
    • Place an insulating mat (or rubber mat) on the lift and remove the battery. If there is foreign substance in the lower protection case, the protection case may be broken due to the battery load, but damage to the battery can be prevented with the insulating mat (or rubber mat).
    • Use a lift with a permissible payload of 700 kg (1543.23 lb) or above and a width of 0.7 m (27.56 in.) to 1.15 m (45.27 in.).
    • Do not lift the BSA too much.
    • Be careful not to rotate the BSA while it is lifted.
    • Lift the BSA with the crane jack and place the lift under the BSA. (Do not move the crane jack)
  2. Install in the reverse order of removal.
    • Install the BSA to the specified torque.
    • If the BSA is dropped, it may cause internal damage. (Do not reuse)
    • Install the BSA using the SST (09375 - BF000).
  3. Refill with coolant. (Refer to Cooling System - "High Voltage Battery Coolant")
  4. Perform the SOC calibration with the KDS. (S/W management → Battery Management System (BMS) → SOC Calibration)
    Refer to the KDS screen for operating conditions and details.

Battery System Assembly (BSA) Inspection Battery Diagnosis for The Partial Module Repair

Battery Diagnosis for The Module Partial Repair

  • If it is necessary to partial repair the high voltage battery, check whether it is possible to partial repair the high voltage battery according to the conditions below.
  • For accurate diagnosis, conduct the diagnosis under the conditions "Keep SOC 20% or above, 25 °C or above for 5 seconds" regardless of mileage and SOH.
  • Do not partial repair the battery module if the conditions below are not met. Problems can occur due to differences in performance between new and existing batteries. Do not partial repair the battery module if the SOH is less than 90%. Problems can occur due to differences in performance between new and existing batteries.

    New parts (%) : 100 Partial repair standard (%) : 90 or more

If the vehicle mileage < 30,000 km (18,000 mile)

If the vehicle mileage > 30,000 km (18,000 mile)

Battery System Assembly (BSA) Inspection Battery State Of Charge (SOC) Inspection

Inspection

  • State of Charge (SOC) refers to the amount of the usable battery in percentage compared to the full-charge capacity of the high voltage battery.
  • SOC calibration should be performed with the KDS to check the correct SOC value after replacing the Battery System Assembly (BSA) or Battery Module Assembly (BMA).
  • When driving after replacing the Battery System Assembly (BSA) or Battery Module Assembly (BMA), it is calibrated to a normal SOC within 30 minutes.
  • Refer to the KDS screen for operating conditions and details.
  1. Check the SOC with the KDS. (Data Analysis → Battery Management System (BMS) → State of Charge of Battery)

Battery System Assembly (BSA) Inspection Battery State Of Health (SOH) Inspection

Inspection

Do not partial repair the battery module if the SOH is less than 90%. Problems can occur due to differences in performance between new and existing batteries.
  • State of Health (SOH) is a figure of merit of the condition of a battery (or a cell, or a battery pack), compared to its ideal conditions.
  • Typically, a battery's SOH will be 100% at the time of manufacture and will decrease over time and use.
  • For operating conditions and details, refer to the diagnostic device (KDS) screen.
  1. Check the SOH with the KDS. (Data Analysis → Battery Management System (BMS) → State of Health of Battery)

    New parts : 100% Partial repair standard : 90% or more

Battery System Assembly (BSA) Inspection Isolation Resistance Inspection

Inspection

  • When working on the high voltage system, the work should be performed by technicians who have completed the relevant training. A lack of understanding of the high voltage system can lead to serious accidents due to electric shock or short circuit.
  • When working on the high voltage system or related components, be sure to observe and be aware of the "Safety Precautions, Cautions and Warnings". If not, it may cause serious accidents due to electric shock or short circuit.
  • When working on the high voltage system, make sure to check the Personal Protective Equipment (PPE) and high voltage shut-off procedure.
  1. Check the Diagnosis Trouble Code (DTC) with the KDS.
    • The insulation resistance value can be checked with the KDS sensor data regardless of the inspection procedure. (Data Analysis → Battery Management System (BMS) → Isolation Resistance)

      Specified value (kΩ) : 300 or above

    • Refer to the KDS screen for operating conditions and details.
  2. When the DTC related to insulation resistance occurs, inspect the problem components by using the fault data. (Refer to DTC guide manual)
    However, if it is impossible to judge whether the insulation breakdown occurred at the front end or rear end, additional information of failure will not be saved.
  3. If it is impossible to check the fault parts, perform the isolation breakdown detection function with the KDS. (Data Analysis → Battery Management System (BMS) → Isolation Breakdown Detection Function)
    Check the insulation breakdown detection components (motors, inverters, etc.) when detection fails.
    Refer to the KDS screen for operating conditions and details.
  4. Check the insulation resistance of the faulty part using a mega ohm tester and replace if necessary.

    Specified value (MΩ) : 2 or above [20 °C]

    Insulation resistance measurement method : Measure the insulation resistance between the ( + ) terminal or the ( - ) terminal and the body (high voltage battery case) while continuously applying a voltage of 1,000 V (approximately for 1 minute).

Battery System Assembly (BSA) Inspection Battery Cell Voltage Inspection

Inspection

  • When battery module repair is required, check the partial repair condition. (Refer to Battery System Assembly (BSA) Inspection - "Battery Diagnosis for The Module Partial Repair)
  • Refer to the below flow chart for battery cell voltage inspection.
  1. Check the battery cell voltage with the KDS. (Data Analysis → Battery Management System (BMS) → Battery Cell Voltage)
    Normal cell voltage (V) : 2.5 - 4.2 Voltage deviation between cells (mV) : 40 or below
    Refer to the KDS screen for operating conditions and details.
  2. Remove the Battery System Assembly (BSA) upper case. (Refer to High Voltage Battery System - "Case")
  3. Measures the voltage of the battery module that contains the faulty cell.
    If the measured voltage is normal, check the sensing circuit (BMU, CMU, wiring, and connector connections).
  4. Replace the Sub-Battery Pack Assembly (Sub-BPA) or Battery Module Assembly (BMA) according to condition for partial repair. (Refer to High Voltage Battery System - "Sub-Battery Pack Assembly (Sub-BPA)") (Refer to High Voltage Battery System - "Battery Module Assembly (BMA)")

Battery System Assembly (BSA) Inspection Air Tightness Inspection

Video Guide

  • This video was created using 3D graphics to help understand the vehicle maintenance manual.
  • There may be some differences from actual vehicles.
  • The location and repair procedures of the parts may vary depending on vehicle model, model year and specifications.
  • Check the KDS Guide for detailed information on how to use the KDS.
  • Check the manual for detailed maintenance procedures.
  • Unauthorized reproduction, distribution, or sharing of this video is prohibited.
BSA Air Tightness Inspection (Pass) (Click to play)

Video: BSA Air Tightness Inspection (Pass)

BSA Air Tightness Inspection (Fail) (Click to play)

Video: BSA Air Tightness Inspection (Fail)

Special Service Tool

Tool Name / Number Illustration Description
EV battery pack Inspecting for air tightness tool
GIT ULT - M100
G7XKDNN001 By GIT
Used for inspecting the air tightness of the Battery System Assembly (BSA) and PE system
Upper Venting valve Sealing Jig
GIT G1DTDNN005 By GIT
Side Venting valve Sealing Jig
G1DTDNN006 By GIT
Helium gas and pressure regulator Used for detecting micro-leakage
(※ Helium gas detectors purchase commercial products)
Helium gas detector

Air Tightness Inspection for High Voltage Battery System and Coolant Line

  • When working on the high voltage system, the work should be performed by technicians who have completed the relevant training. A lack of understanding of the high voltage system can lead to serious accidents due to electric shock or short circuit.
  • When working on the high voltage system or related components, be sure to observe and be aware of the "Safety Precautions, Cautions and Warnings". If not, it may cause serious accidents due to electric shock or short circuit.
  • When working on the high voltage system, make sure to check the Personal Protective Equipment (PPE) and high voltage shut-off procedure.
  • After working on the Battery System Assembly (BSA) or Sub-Battery Pack Assembly (Sub-BPA), perform the air tightness inspection by using the EV Battery Pack Air leak Tester.
  • Drain the coolant in BSA before checking it.
The air tightness inspection procedures are proceeding in order of the coolant line and then the BSA.
  1. Remove the BSA. (Refer to High Voltage System - "Battery System Assembly (BSA)")
  2. Connect the EV battery pack airtight check tester equipment and KDS.
  3. Scan the QR code on the high voltage battery upper case. (S/W management → Battery Management System (BMS) → High Voltage Battery Pack & Coolant Line Leak Test)
    • If the QR code cannot be scanned, enter the battery code at the bottom of the QR code directly.
    • Refer to the KDS screen for operating conditions and details.
  4. Perform the coolant drain by using the KDS.
    1. Install the coolant adapter (A, B).
    2. Connect the hose (B) to inlet adapter (A).
    3. Connect the opposite side of inlet hose (A) to air pressure line of SST (ULT-M100).
    4. Install the hose (B) to the outlet adapter (A) and put the opposite of hose to a bucket.
      Use the clean beaker to prevent mixing with other fluid or oil.
    5. Follow the procedure on KDS to Drain the coolant by opening the outlet adapter valve (A) slowly.
      Slowly open the outlet adapter valve as the coolant may vent at high pressure.
  5. inspect the high voltage battery system & coolant line air tightness with the KDS. (S/W management → Battery Management System (BMS) → High Voltage Battery Pack & Coolant Line Leak Test)
    Refer to the KDS screen for operating conditions and details.
  6. Perform the air tightness inspection according to KDS screen description.
    1. Install the BSA front sealing connector (E006)(A).
    2. Install the Battery Management Unit (BMU) sealing connector (E004)(A).
    3. Install the BSA rear sealing connector (E007)(A).
    4. Install the Integrated Charging Control Unit (ICCU) sealing connector (E008)(A).
    5. Install the Upper Venting valve Sealing Jig (A).
      • Wipe the venting valve surface (A) using a clean cloth before installing the sealing jig
      • Wipe the O-Ring (A) using a clean cloth before installing the sealing jig.
      • Make sure that the adapter is properly attached to the pressure regulator. Pressure may leak if the adapter is not completely attached.
  7. Check the results after inspecting the BSA air tightness.
    • If the results of the air tightness inspection fail, check the leakage area by referring to the procedures below.
    • Helium gas, pressure regulator, and leak detector are required to check for leak area.
    • Helium, regulators, and helium gas detectors purchase commercial products to detect micro-leakage (0.1 - 0.3 mbar) and secure complete confidentiality of the pack.
    1. Attach the adapter (A) to the pressure regulator.
      Make sure that the adapter is properly attached to the pressure regulator. Pressure may leak if the adapter is not completely attached.
    2. Install the adapter hose (A) to the helium gas valve.
    3. Attach the pressure sensor module (A) to the pressure regulator.
      Make sure that the adapter is properly attached to the pressure regulator. Pressure may leak if the adapter is not completely attached.
    4. Install the pressure sensor module (A) to the SENSOR INPUT of air tightness equipment.
    5. Pressurize the helium gas to 500 mbar for 30 seconds, then proceed to close the injection valve.
      • Be careful not to exceed the pressurization time. Excessive internal pressure in the battery (over 20 - 30 mbar) may cause deformation of the upper case.
      • Pressurizing helium to 500 mbar for 100 seconds using a pressure regulator applies approximately 20 mbar inside the battery.
    6. Check the leakage area in the Battery System Assembly (BSA) by using the leak tester.
      • Check the welded part of the lower case and the connection part of the battery connector.
      • In many cases where air tightness cannot be maintained near the gasket. Therefore, around the gasket is mainly checked with a detector.

Case Components and Components Location

Component

Upper Case

1. Upper Case Bolt
1-a. 103.0 - 155 N·m
2. O-Ring
3. Upper Case
3-a. Step 1 : 8,8 N·m
3-a. Step 2 : 10,8 N·m
4. Waterproof Gasket

Lower Case

1. Upper Case Bolt
1-a. 103.0 - 155 N·m
2. O-Ring
3. Upper Case
3-a. Step 1 : 8,8 N·m
3-a. Step 2 : 10,8 N·m
4. Waterproof Gasket
5. Power Relay Assembly (PRA)
5-a. Step 1 : 8,8 N·m
5-a. Step 2 : 10,8 N·m
6. Battery Management Unit (BMU)
6-a. 7.8 - 11,8 N·m
7. Cell Monitoring Unit (CMU)
7-a. 7.8 - 11,8 N·m
8. Sub-Battery Pack Assembly (Sub-BPA)
8-a. Step 1 : 8,8 N·m
8-a. Step 2 : 10,8 N·m
9. Main Fuse
9-a. 7.8 - 11,8 N·m
10. Lower Case

Case Removal and Installation

Removal

  • When working on the high voltage system, the work should be performed by technicians who have completed the relevant training. A lack of understanding of the high voltage system can lead to serious accidents due to electric shock or short circuit.
  • When working on the high voltage system or related components, be sure to observe and be aware of the "Safety Precautions, Cautions and Warnings". If not, it may cause serious accidents due to electric shock or short circuit.
  • When working on high voltage system, make sure to check the Personal Protective Equipment (PPE) and high voltage shut-off procedure.
  • After an accident, check the high voltage battery sensor data (insulation resistance, voltage deviation between cells, DTCs, etc.) and internal damage.
  • When replacing the high voltage battery case with a fine deformation, only the case is exchanged after checking the change in the high voltage battery sensor data.
  • Perform the air tightness inspection with the KDS after repairing the battery.
  • If the battery system assembly (BSA) is not completely sealed and there is a leak in the cooling water line, it may cause serious failure of the BSA.
Upper Case
  1. Remove the Battery System Assembly (BSA). (Refer to High Voltage Battery System - "Battery System Assembly (BSA)")
  2. Remove the high voltage battery system upper case bolts (A).

    Tightening torque : 103.0 - 155 N·m

    Use the a hex socket or wrench when removing the upper bolt.
  3. Remove the high voltage battery system upper case (A).
    Tightening torque Step 1 : 8,8 N·m Step 2 : 10,8 N·m
    • When removing the upper case to prevent deformation, work for at least two people.
    • Recommend to transfer with the horizontal rather than the longitudinal due to cause transformed in the case of removing the case asymmetrically or pressing the load momentarily.
    • The watertight bracket is integrated with the upper case.
  4. Remove the main fuse. (Refer to High Voltage Battery Control System - "Main Fuse")
  5. Remove the Battery Management Unit (BMU). (Refer to High Voltage Battery Control System - "Battery Management Unit (BMU)")
  6. Remove the Power Relay Assembly (PRA). (Refer to High Voltage Battery Control System - "Power Relay Assembly (PRA)")
  7. Remove the Cell Monitoring Unit (CMU). (Refer to High Voltage Battery Control System - "Cell Monitoring System (CMU)")
  8. Remove the Sub-Battery Pack Assembly (Sub-BPA). (Refer to High Voltage Battery System - "Sub Battery Pack Assembly (Sub-BPA)")
  9. Remove the front high voltage junction box connector assembly (A) after removing the bolts.
    Tightening torque Step 1 : 8,8 N·m Step 2 : 10,8 N·m
  10. Remove the Integrated Charging Control Unit (ICCU) connector service cover (A) after removing the bolts.

    Tightening torque : 7.8 - 11,8 N·m

  11. Remove the ICCU connector assembly (A) after removing the bolts.
    Tightening torque Step 1 : 8,8 N·m Step 2 : 10,8 N·m
  12. Remove the rear high voltage junction box connector assembly (A) after removing the bolts.
    Tightening torque Step 1 : 8,8 N·m Step 2 : 10,8 N·m
  13. Remove the BMU connector assembly (A) after removing the bolts.
    Tightening torque Step 1 : 8,8 N·m Step 2 : 10,8 N·m
  14. Remove the all wiring harness after disconnecting the connectors and removing the fasteners.
  15. Remove the lower case (A).
Lower Case

Installation

  • When working on the high voltage system, the work should be performed by technicians who have completed the relevant training. A lack of understanding of the high voltage system can lead to serious accidents due to electric shock or short circuit.
  • When working on the high voltage system or related components, be sure to observe and be aware of the "Safety Precautions, Cautions and Warnings". If not, it may cause serious accidents due to electric shock or short circuit.
  • When working on high voltage system, make sure to check the Personal Protective Equipment (PPE) and high voltage shut-off procedure.
  1. Apply a new gap filler with the Special Service Tool (SST). (Refer to High Voltage Battery System - "Gap Filler Application")
  2. Perform the High Voltage Battery Pack Connector Check with the KDS before installing the Battery System Assembly (BSA) upper case. (S/W Management → Battery Management System (BMS) → High Voltage Battery Pack Connector Check)
    Refer to the KDS screen for operating conditions and details.
  3. Install in the reverse order of removal.
    • Install the case to the specified torque.
    • In order to maintain the confidentiality of the Battery System Assembly (BSA), replace the case if any deformation occurs.
    • When removing the upper case to prevent deformation, work for at least two people.
    • Recommend to transfer with the horizontal rather than the longitudinal due to cause transformed in the case of removing the case asymmetrically or pressing the load momentarily.
    • The upper case bolts (A) are different, so check the shape and tighten them to the correct position.
    • The existing O-rings of the upper case bolt should be replaced with new ones (do not reuse).
    • The existing gasket of the upper case should be replaced with new one (do not reuse).
  4. Perform the air tightness inspection with the KDS. (Refer to High Voltage Battery System - "Air Tightness Inspection")

Gap Piller application Procedure Description and Operation

Description

  • The battery for an EV heats up during charging and discharging. The gap filler that is made from the material, like silicone, is needed to cool the heat out of the battery.
  • The gap filler is used to fix the Battery Module Assembly (BMA) to the battery lower case, absorb the vibration and insulate.
  • The gap filler is to improve low thermal conductance due to the space between the module and pack, the thermal conductance will be low without the gap filler. Plus, the thermal conductivity is low as the gap between the modules increases.
  • If the gap is filled with the gap filler to the space, it is minimized. In addition, the heat from the cells is emitted externally.
  • Silicone for the radiation of heat, such as gap filler, is used in major components such as inverters, converters, motors, etc., in addition to the high voltage battery.

Gap Piller application Procedure Gap Piller application Procedure

Special Service Tool

Tool Name / Number Illustration Description
Application guide
0K375 - CV210
Used for applying the high voltage battery gap filler
Application nozzle
0K375 - CV220
Application support
0K375 - CV230
Application dispenser gun
0K375 - CV300
TGF-NT300UL 530g cartridge
0K375 - AV300
Static mixer
09375 - GI230

Refer to the contact information below for special tools (0K375 - CV220, CV230, CV300) for gap filler application
  • TOOL & TECH (overseas@toolntech.com)

[Gap Piller application Procedure]

  • When working on the high voltage system, the work should be performed by technicians who have completed the relevant training. A lack of understanding of the high voltage system can lead to serious accidents due to electric shock or short circuit.
  • When working on the high voltage system or related components, be sure to observe and be aware of the "Safety Precautions, Cautions and Warnings". If not, it may cause serious accidents due to electric shock or short circuit.
  • When working on high voltage system, make sure to check the Personal Protective Equipment (PPE) and high voltage shut-off procedure.
  • Do not step on or apply a load when applying the gap filler. It may cause damage or transform when a load is applied.
  • If the gap filler application surface is damaged, it must be reapplied with new gap filler.
  • The application nozzle (0K375 - CV220) discards after use on the same day. (Do not reuse)
  1. Remove the Sub-Battery Pack Assembly (Sub-BPA). (Refer to High Voltage Battery System - "Sub Battery Pack Assembly (Sub-BPA)")
  2. Remove the Cell Monitoring Unit (CMU). (Refer to High Voltage Battery Control System - "Cell Monitoring System (CMU)")
  3. Remove the remaining gap filler on the Sub-BPA downside surface and the lower case.
    • Remove the residual gap filler as possible by hand and using an air blow gun.
    • A few of the existing gap filler can remain on the surface. (It doesn't cause the serious performance problem)
    • It may cause damage to the BMA downside surface or lower case when removing the gap filler by using the sharp tools like a blade.
  4. Install the TGF-NT300UL 530g cartridge (0K375 - AV300) and the application dispenser gun (0K375 - CV300).
    • Be assemble all of the Special Service Tool (SST) by referencing the SST manual.
    • Cut the static mixer (09375 - GI230) leaving the last layer of the static mixer as below.
  5. Set to the 6 bar after installing the air hose (B) on the application dispenser gun (0K375 - CV300) (A).
    When the pressure sets above the specification (6 bar), the TGF-NT300UL 530g cartridge (0K375 - AV300) is damaged.
  6. Discard about the first 10 cm (3.94 in.) of the gap filler in order to removed the unmixed gap filler.
  7. Install the application guide (0K375 - CV210) (A).
    Check the IN and OUT direction of the nozzle when installing the application guide (0K375 - CV210).
  8. Fix the application guide (0K375 - CV210) (A) by installing the fixing pins (B,C).
    • The mounting location of the fixing pin is as below.
    • Install the fixing pin (B) as it does not interfere with the applied surface.
  9. Install the application dispenser gun (0K375 - CV300) (A) on the application guide (0K375 - CV210) (B).
  10. Fix the application support (0K375 - CV230) handle (A) after adjusting it.
  11. Release the rail by loosening the wing bolts (A).
  12. Apply the gap filler equally after install the fixing pin (A) by pressing the trigger.
    • Move the gap filer application guide after applying the gap filler enough without gap.
    • 530 g cartridge uses for 1 room and it will still have a little left after applying gap filler.
    • Do not reuse the cartridge which is residual after applying.
  13. Remove the trigger fixing pin (A) after completing the gap filler application.
  14. Fix the rail by tightening the wing bolts (A).
  15. Remove the gap filler application dispenser (0K375 - CV300) (A) from the gap filler guide (0K375 - CV210).
    Remove the dispenser (0K375 - CV300), taking care not to damage the surface to which the gap filler is applied.
  16. Remove the gap filler application guide (0K375 - CV210) (A) after removing the fixing pins (B,C).
    Remove the gap filler application guide (0K375 - CV210) and fixing pins vertically, taking care not to damage the surface to which the gap filler is applied.
  17. Clean the application nozzle (0K375 - CV220) and rail before the second application.
    It may cause the bubbles if the residual gap filler is not removed completely.
  18. Change the TGF-NT300UL 530g cartridge (0K375 - AV300).
  19. Apply the gap filler in the same order as above.
  20. Install in the reverse order of removal.
    • Install the Sub Battery Pack Assembly (Sub-BPA) within 90 minutes and at room temperature [25 °C] before the gap filler is hardened.
    • Be careful not to damage the surface to which the gap filler was applied, when installing the Cell Monitoring Unit (CMU).
    • Install the Battery Module Assembly (BMA) to specified torque following the below orders.

Sub-Battery Pack Assembly (Sub-BPA) Components and Components Location

Component

1. Upper Case Bolt
1-a. 103.0 - 155 N·m
2. O-Ring
3. Upper Case
3-a. Step 1 : 8,8 N·m
3-a. Step 2 : 10,8 N·m
4. Waterproof Gasket
5. Sub-Battery Pack Assembly (Sub-BPA)
5-a. Step 1 : 8,8 N·m
5-a. Step 2 : 10,8 N·m
6. Battery Module Assembly (BMA)
6-a. 7.8 - 11,8 N·m

Sub-Battery Pack Assembly (Sub-BPA) Removal and Installation ➤