Metal primer
1K corrosion protection wash primer
Designation:
- 1K corrosion protection wash primer -ALN 002 003 10-
Product description
The 1K corrosion protection primer is a zinc chromate-free one-component product based on polyvinyl butyral for passenger car repair.
Its special pigment and binder composition provides good corrosion protection and good adhesion, and it also has a weld-through test certificate. However, this product is not conductive and therefore not suitable for spot welding.
For residual rust spots, at edges and corners, and at bare sanded areas, we recommend topcoating 1K corrosion protection wash primer -ALN 002 003 10- with a 2K HS surfacer.
Application information
Substrate
Suitable substrates:
- cleaned and sanded, electrogalvanized steel panels or soft aluminum
- sanded factory primer
- cured, solvent-resistant, well-preserved and sanded original or old paint finish (excluding thermoplastic paint)
- surfaces pre-worked with 2K polyester products and then finely sanded
Pretreatment of substrates:
- Clean thoroughly with silicone remover -LVM 020 000 A5- or long-acting silicone remover -LVM 020 100 A5-.

- Dry sand with a dual-action sander and dust extraction, P400-500 grit.

- Wet sand with P800-1000 grit sandpaper. Remove any rust spots thoroughly and feather the transitions to the old paint finish.

Processing
Thinnable with:
- 2K thinner -LVE 009 001 A5-
- 2K thinner, plus -LHA 014 000 A5-
- 2K thinner, special -LVM 009 200 A2/A5-
Application method "Spray pass"

- Application viscosity 4 mm at +20 °C, DIN 53211

Thinner addition of 40 % at +20 ºC material temperature
- When adding thinner, use a measuring stick during mixing.

Application viscosity, 4 mm flow cup, "Compliant" and "HVLP" spray guns:
DIN 4 mm: 18-20 seconds.
ISO 4 mm: 44-53 seconds.
- Set the spray nozzle (see manufacturer's specifications): "Compliant" and "HVLP" 1.3-1.4 mm.
- Set the spray pressure (see manufacturer's specifications): "Compliant" 1.5-3.0 bar.

- Apply in 2 spray passes.
- The specified dry film thickness is 15-20 µm.
Application method "Spread on"
![]()
Note
- For the application method "brushing", brush the material 1-2 times nonstop.
- In this case, the supplied viscosity is equal to the application viscosity.

Flash-off time: at +20 °C room temperature 15-25 minutes

Overcoating
Recommended build-up:
- Filling with 2K HS filler
![]()
Caution!
Do not recoat with polyester products.
Do not recoat with epoxy products.
Do not recoat directly with waterborne basecoat.
Do not use over thermoplastic coatings.
The following 3-layer build-up is recommended:
- Primer with 1K corrosion protection wash primer -ALN 002 003 10-
- Isolation with 2K HS filler
- Topcoat
On galvanized substrates the 3-layer build-up is absolutely required.

Personal protective equipment:
- Observe the safety data sheet
- Wear personal protective equipment during application
Characteristics


Storage
Guaranteed storage stability is 24 months from production date. Use by the date stated on the label at the latest when stored in sealed original containers at +20 °C.

1K wash primer
Designation:
- 1K wash primer -LVM 044 007 A2-, colour light grey
- 1K wash primer -LVM 044 171 A2-, colour dark grey
Product description
The 1K wash primer is a zinc chromate-free one-component wash primer for all common metallic substrates.
- suitable for all common metallic substrates
- VOC compliant and offers good corrosion protection properties
- easy handling (1K material)
- Welding test certificate available.
- Available in light grey and dark grey
Application information
Substrate
Suitable substrates:
- Steel
- cleaned and sanded, electrogalvanized steel panels or soft aluminum
- sanded factory primer (not on large areas of sanded KTL primer on new parts)
- well-sanded original or refinish paint (except thermoplastic coating)
- surfaces pre-worked with 2K polyester products and then finely sanded
![]()
Note
Due to the variety of alloys and manufacturing processes for metals, a preliminary test on the respective substrate is required to ensure the pretreatment is sufficient for perfect adhesion.
Pretreatment of substrates:
- Clean thoroughly with silicone remover -LVM 020 000 A5- or long-acting silicone remover -LVM 020 100 A5-.

- Clean the factory or original paint and sand it, thoroughly remove any rust spots and feather the edges into the existing paint.

- Use a suitable cleaner before overcoating to ensure a clean, residue-free surface.

Processing
Thinnable with:
- 2K thinner -LVE 009 001 A5-
- 2K thinner, plus -LHA 014 000 A5-
- 2K thinner, special -LVM 009 200 A2/A5-
- 2K thinner, slow -LVM 009 300 A2- (for large objects and high temperatures)
Application method "Spray pass"

- Processing viscosity 4 mm at +20 °C, DIN 53211 is the mixed viscosity.
Thinner addition of 50 % at +20 °C material temperature

- When adding thinner, use a measuring stick during mixing.
Application viscosity, 4 mm flow cup, "Compliant" and "HVLP" spray guns:
DIN 4 mm: 18-20 seconds
ISO 4 mm: 36-45 seconds

- Set spray nozzle (see manufacturer's data): "Compliant" and "HVLP" 1.3-1.5 mm.
- Set spray pressure (see manufacturer's specifications): "Compliant" 2.0–2.5 bar.

- When used as wash primer, apply one spray coat.
- Specified dry film thickness is 10-15 µm.
![]()
Note
Isolation of small sanded-through spots may only be carried out with waterborne basecoat or 2K HS topcoat using the wet-on-wet and interim-sanding method on the 1K wash primer -LVM 044 007 A2-/-LVM 044 171 A2- if the sanded-through spot is not larger than Ø 5.0 cm.

Flash-off time at +20 °C room temperature, recoatable after:
- 10-15 minutes with 2K HS filler.
- 20-30 minutes with waterborne basecoat (only for small sanded-through spots)
- 10-15 minutes with 2K HS topcoat (only for small sanded-through spots)
- 45-60 minutes sandable

Overcoating


Can be overcoated with:
- Waterborne basecoat and 2K HS clearcoat (only for small sanded-through spots)
- 2K HS topcoat (only for small sanded-through spots)
![]()
Caution!
Do not recoat with polyester products.
Do not use over thermoplastic coatings.
Do not recoat with epoxy products.
Do not recoat with waterborne products.
Not dry-sandable.
Personal protective equipment:
- Observe the safety data sheet
- Wear personal protective equipment during application
Characteristics


Storage
Guaranteed storage stability is 24 months from production date. Use by the date stated on the label at the latest when stored in sealed original containers at +20 °C.

2K wash primer
Designation:
- 2K wash primer -LHV 043 000 A2-
Product description
The 2K wash primer is a zinc chromate- and phenol-free acid-curing two-component wash primer from our PVB system.
- excellent corrosion protection through passivating properties
- for metallic substrates, especially aluminium and galvanised steel sheet
- easy processing properties
- Colour olive grey
Application information
Substrate
Suitable substrates:
- bare steel sheet, cleaned and sanded
- cleaned and sanded, electrogalvanized steel panels or soft aluminum
- sanded factory primer
- well-sanded original or refinish paint (except thermoplastic coating)
- surfaces pre-worked with 2K polyester products and then finely sanded
Pretreatment of substrates:
- Clean thoroughly with silicone remover -LVM 020 000 A5- or long-acting silicone remover -LVM 020 100 A5-.

- Clean the factory or original paint and sand it, thoroughly remove any rust spots and feather the edges into the existing paint.

- Use a suitable cleaner before overcoating to ensure a clean, residue-free surface.

Processing
Mixing ratio:
- 1:1 by volume with 2K additive solution -LHA 004 000 A2-
Pot life:
- Spray-ready after 8-10 hours at +20 °C
![]()
Note
Mixed material must be used the same day.

Application method "Spray pass"

- Application viscosity 4 mm at +20 °C, DIN 53211
Application viscosity, 4 mm flow cup, "Compliant" and "HVLP" spray guns:
DIN 4 mm: 16-18 seconds

- Set spray nozzle (see manufacturer's data): "Compliant" 1.2-1.4 mm.
- Set spray nozzle (see manufacturer's data): "HVLP" 1.3-1.5 mm.
- Set spray pressure (see manufacturer's specifications): "Compliant" 2.0–2.5 bar.
- Set atomizing air pressure (see manufacturer's specifications): "HVLP" 0.7 bar.

- Specified dry film thickness is 8-12 µm.

Drying
Air drying at +20 °C room temperature, can be overspray-coated after 30 minutes
![]()
WARNING!
Forced drying and IR drying is not possible, as interlayer adhesion problems may occur.

Overcoating
After flash-off at +20 °C, can be overspray-coated with 2K HS filler.
Then can be overcoated with:
- Waterborne basecoat and 2K HS clearcoat
- 2K HS topcoat
![]()
Caution!
Do not recoat with polyester products, epoxy products or waterborne products.
Do not use over thermoplastic coatings.
Do not recoat directly with waterborne basecoat or 2K HS topcoat.

Personal protective equipment:
- Observe the safety data sheet
- Wear personal protective equipment during application
Characteristics


![]()
Note
The coverage was calculated taking into account the recommended film thickness and the percentage volume solids (excluding thinner addition). The corresponding processing losses were likewise not taken into account.
Storage
Guaranteed storage stability is 24 months from production date. Use by the date stated on the label at the latest when stored in sealed original containers at +20 °C.