Pcv Valve
Removal
REMOVAL
The necessary procedures (adjustment, calibration, initialization or registration) that must be performed after parts are removed and installed, or replaced during PCV valve (ventilation valve sub-assembly) removal/installation are shown below.
Necessary Procedures After Parts Removed/Installed/ReplacedReplaced Part or Performed Procedure | Necessary Procedure | Effect/Inoperative Function when Necessary Procedure not Performed | Link |
|---|---|---|---|
|
Inspection after repair |
|

Procedure | Part Name Code | ![]() | ![]() | ![]() |
|
|---|---|---|---|---|---|
1 |
INTAKE MANIFOLD |
17111 |
- |
- |
- |
2 |
VENTILATION HOSE |
12261 |
- |
- |
- |
3 |
PCV VALVE (VENTILATION VALVE SUB-ASSEMBLY) |
12204 |
- |
- |
|
★ |
Precoated part |
- |
- |
PROCEDURE
1. REMOVE INTAKE MANIFOLD
Click here ![]()
2. DISCONNECT VENTILATION HOSE

3. REMOVE PCV VALVE (VENTILATION VALVE SUB-ASSEMBLY)

(1) Using a 22 mm ball joint lock nut wrench, remove the PCV valve (ventilation valve sub-assembly) from the No. 1 ventilation case.
Inspection
INSPECTION
PROCEDURE
1. INSPECT PCV VALVE (VENTILATION VALVE SUB-ASSEMBLY)
Pre-procedure1
(a) Install a clean hose to the PCV valve (ventilation valve sub-assembly).
Procedure1
(b) Check the PCV valve (ventilation valve sub-assembly) operation.
(1) Blow air into the No. 1 ventilation case side, and check that air passes through easily.

*a |
Hose |
*b |
Air |
![]() |
No. 1 Ventilation Case Side |
CAUTION:
Do not suck air through the valve.
Petroleum substances inside the valve are hazardous to your health.
If the result is not as specified, replace the PCV valve (ventilation valve sub-assembly).
(2) Blow air into the intake manifold side, and check that air passes through with difficulty.

*a |
Hose |
*b |
Air |
![]() |
Intake Manifold Side |
CAUTION:
Do not suck air through the valve.
Petroleum substances inside the valve are hazardous to your health.
If the result is not as specified, replace the PCV valve (ventilation valve sub-assembly).
Post-procedure1
(c) Remove the hose from the PCV valve (ventilation valve sub-assembly).
Installation
INSTALLATION
COMPONENTS (INSTALLATION)
Procedure | Part Name Code | ![]() | ![]() | ![]() |
|
|---|---|---|---|---|---|
1 |
PCV VALVE (VENTILATION VALVE SUB-ASSEMBLY) |
12204 |
- |
- |
|
2 |
VENTILATION HOSE |
12261 |
- |
- |
- |
3 |
INTAKE MANIFOLD |
17111 |
- |
- |
- |
![]() |
N*m (kgf*cm, ft.*lbf): Specified torque |
* |
For use with a 22 mm ball joint lock nut wrench |
![]() |
Adhesive 1324 |
★ |
Precoated part |
PROCEDURE
1. INSTALL PCV VALVE (VENTILATION VALVE SUB-ASSEMBLY)

*a |
Adhesive 1324 |
*b |
Torque Wrench Fulcrum Length |
(1) Apply adhesive to the PCV valve (ventilation valve sub-assembly).
Adhesive:
Toyota Genuine Adhesive 1324, Three Bond 1324 or equivalent
(2) Using a 22 mm ball joint lock nut wrench, install the PCV valve (ventilation valve sub-assembly) to the No. 1 ventilation case.
Torque:
Specified tightening torque :
20 N·m {204 kgf·cm, 15 ft·lbf}
NOTICE:
Do not start the engine for at least 1 hour after installation.
HINT:
- Calculate the torque wrench reading when changing the fulcrum length of the torque wrench.
Click here

- When using a 22 mm ball joint lock nut wrench (fulcrum length of 149.75 mm (5.90 in.)) torque wrench (fulcrum length of 162 mm (6.38 in.)): 10 N*m (102 kgf*cm, 7 ft.*lbf)
2. CONNECT VENTILATION HOSE
3. INSTALL INTAKE MANIFOLD
Click here ![]()